Outlay Blog Estimating basics

How to read a construction estimate, line by line

CSI codes, units, direct cost and markups: what each column and each line of an estimate means, and where the mistakes usually hide.

An estimate is a table. Learn what each column is for and how the lines at the bottom stack up, and you can check one in a few minutes.

The columns

  • CSI code. A six-digit number from MasterFormat, the filing system the industry uses for construction work. The first two digits are the division: 03 is concrete, 09 is finishes, 26 is electrical. Codes keep an estimate in the same order as the specification, so scope can be compared section by section.
  • Description. What the item is, specific enough to buy: "gypsum board, 5/8 inch type X", not "drywall".
  • Quantity and unit. How much, and measured in what. SF is square feet, LF linear feet, CY cubic yards, EA each, LS lump sum. A lump sum is a line that was not measured, so ask what is in it.
  • Unit cost. The cost of one unit, installed. In a detailed estimate it is split into material, labor and equipment.
  • Total. Quantity multiplied by unit cost.

The lines at the bottom

The totals of all the lines add up to the direct cost: what it costs to buy and install the work. Then come the lines that turn cost into a price.

  • General conditions. The cost of running the job: supervision, site office, temporary power, dumpsters, insurance, permits.
  • Overhead. The cost of running the company, spread across its jobs.
  • Profit. What is left for the contractor.
  • Contingency. Money for what the drawings do not yet show. It should shrink as the design gets more complete.

Check what each percentage is applied to. Ten percent profit on direct cost is a smaller number than ten percent on direct cost plus general conditions and overhead.

Where the mistakes hide

  1. Missing scope. Compare the divisions in the estimate with the divisions in the specification. A division that is in the specification and not in the estimate is either excluded or forgotten.
  2. Wrong units. Carpet priced per square yard against a quantity in square feet is wrong by a factor of nine.
  3. Double counting. Wall base in both the flooring and the carpentry sections. Blocking in both framing and drywall.
  4. Lump sums. A few are normal. An estimate that is mostly lump sums has not been measured.
  5. Old drawings. Check the drawing dates and addenda listed on the estimate against the current set.

The summary page

Most estimates end with a summary by division and a cost per square foot. The cost per square foot is useful for one thing: comparing against similar buildings to see whether the total is in a believable range. It is not a way to price a building.

30% off

First job with us? It costs less.

New clients get 30% off their first project with Outlay. You see the fee and the delivery date before any work starts.

Upload plans

More from the blog

New clients

30% off

your first estimate

Upload your plans and we reply with the discounted fee and a delivery date. You decide after that, and you owe nothing if you say no.

Upload plans