Outlay Sample projects Single-storey retail shell
Sample project, commercial
Single-storey retail shell
The estimate a general contractor would carry into bid day for a retail shell, with the building kept separate from its parking and site utilities.
- Size
- 12,000 SF
- Construction
- Masonry walls, steel joists and deck, slab on grade
This one is made up to show how an Outlay estimate is laid out. It is not a client project. Send your own plans for a real one.
| Slab on grade | 12,000 SF |
|---|---|
| Concrete block | 9,600 SF |
| Structural steel and joists | 54 TON |
| TPO roofing | 12,400 SF |
| Storefront | 1,850 SF |
| Asphalt paving | 4,200 SY |
Sheet 2 of 4
The estimate, summarised by division
The first page of the spreadsheet. Behind each division is a section of measured lines, like the ones on our trade pages.
| Division | Scope | Share of direct cost | Total |
|---|---|---|---|
| 03 | Concrete | 9.3% | 168,000 |
| 04 | Masonry | 11.7% | 212,000 |
| 05 | Metals | 15.8% | 286,000 |
| 07 | Thermal and moisture protection | 11.0% | 198,000 |
| 08 | Openings | 6.9% | 124,000 |
| 09 | Finishes | 5.3% | 96,000 |
| 21 | Fire suppression | 3.0% | 54,000 |
| 22 | Plumbing | 3.8% | 68,000 |
| 23 | HVAC | 9.5% | 172,000 |
| 26 | Electrical | 10.4% | 188,000 |
| 31-32 | Sitework and paving | 13.3% | 240,000 |
| Direct cost | 1,806,000 | ||
| General conditions, 8% | 144,480 | ||
| Overhead and profit, 10% | 195,048 | ||
| Estimate total | $2,145,528 | ||
| Cost per square foot | $179 | ||
Illustrative figures for a sample project, not a quote and not a guide to what your project will cost. Your estimate uses your drawings, your location and your markups.
Sheet 3 of 4
How this one is laid out
In the spreadsheet
- Shell and site kept as separate sections
- Tenant fit-out excluded and listed as an exclusion
- Alternates priced as add or deduct lines
- Waste factors and markups as separate figures you can change
Trades in this project
30% off
First job with us? It costs less.
New clients get 30% off their first project with Outlay. You see the fee and the delivery date before any work starts.
See the other sample projects, or the sample estimate linked to its plan.
Sheet 4 of 4
Send your plans for a quote
You get an email back with the fee and the delivery date. After that it is your call.
- No card needed to get a quote
- Your drawings stay confidential
- A person reads every request
- New clients: 30% off your first estimate
Plans sent
A person reads every request. If your bid is due soon and you have not heard from us, reply to our email or write to [email protected].